Wednesday 28 June 2017

Special volunteers today

We were honoured to receive a visit from Steam Railway today, to lend us a hand with volunteering. Every little bit helps, you might say, but it's good to see the railway press take an interest in our extension.
Toby Jennings and Thomas Bright came down to muck in with the gang, then visit Broadway to see how things were going there.

First things first, a nice cup of tea in the mess coach at Toddington, and, novelty here, some doughnuts brought in by Paul, an idea that has wafted over from the Hayles group. A good idea! The doughnuts seem to have found favour in the PWay gang, if one may believe the photograph. No nasty Dalmatians to sniff at them either.

After the daily briefing, we split into 3 teams:

- Sleeper stacking at Gotherington
- Repair of a joint in Toddington (urgent)
- Work on the extension.

At first it seemed as if only 4 volunteers had turned up. In the mess coach we were puzzled. There was a very large teapot of hot tea, and no one to drink it. Yet we were 20 souls booked on Doodle - where were they?

They were in the yard at Toddington, watching the pride of the P&O group being loaded on to a low loader, with its tender on a second one. The destination is the Mid - Hants. Some distraction for the gang then.



With the distractions, repair and sleeper stacking, we were only 3 to start with at Childswickham.

We decided to equip this long stretch of newly laid sleepers with the necessary pads, so that rails could be laid on them on Saturday.

Here you can see them just completing this task.




The Landie had to go to Winchcombe to fetch materials for the repair at Toddington first, but did finally arrive at the rail head with the rail drilling equipment. Here a sub-team of the extension one set out to continue rail drilling up to the current end of the rails laid. The Saturday team had managed a respectable 9 sets of fishplates mounted, and in the foreground is the next one, the tenth.

An issue we met was that the enormous heat we have had also affected the recently laid rail north of the supply train. A slight buckle could be made out, and many of the rail joints were all but closed up; others now too wide apart. It didn't stop us drilling the holes, but because of the ajustments required, we didn't get many fishplates mounted.





Here we see Martin and Clive prepping the rail drill, which needed a bit fixing to the front.

Then refuelling, and arranging for a supply of cutting fluid in the pump.








The rail drill is mounted over a base plate, which ensures you drill the two holes in each rail end exactly the right distance appart.

You also get the choice of holes for 95lb rail, or 113lb. Of course the hole spacings are different!







After drilling the first of two holes, it becomes apparent that the sleeper is too close to drill the second. You need to move the sleeper. The jack to lift the rail off is 1/4 mile away in the site safe; the Landie has gone to Winchcombe to get more Pandrol clips. One brave volunteer carries the heavy Duff jack the whole distance,  but now we are clear, the second hole is drilled and the fishplates can go on.






Later in the day we get to the 5th and last set of holes to be drilled (20 in all).

Beyond is the gap to allow vehicles to cross, then more sleepers up to the bridge.






That gap for vehicles is in regular use. Here is the Landie, returning from a Pandrol clip delivery run.





The pad laying sub team finished their job, and then turned to laying out Pandrol clips. These were taken off the Landie in bags, and dropped alongside at regular intervals. Not too much carrying here then.





Laying out the Pandrol clips was an ideal job for the team from Steam Railway - here they are, Toby and Thomas, with a bag each. Thanks for your help, guys!

Thomas also helped with adjusting the fishplate spacings. The rail was moved along a few millimetres by using wedges to prise open the offending joints. Clive hovers with the tape measure. You can't wedge the rails back if you overshoot.

A shot near the end of the day across Pry Lane bridge shows the clipped up rail extending into the distance. Just a few more yards to go to the next bridge, and the start of the Broadway goods yard.


Canopy update

The canopy team at Broadway have been on site several days in a row. Almost all of the steelwork is now assembled, with just a few extra bits to go at each end to support the wooden framework at the ends.

Generally speaking, it's been days of drilling holes followed by days of riveting. Yesterday was a riveting day, as tomorrow will be. We've done the easy bits along the fascia board, and have now been along the ridge purlin - the one with the arches - to attach the purlins to each other, and to the trusses underneath.





Although we drill the holes beforehand and fit them with temporary bolts, some minute lateral movement when they are removed for riveting can mean that the holes need further drilling out with the air powered drill.










And this is the result - 4 neat rivets in the support for a middle purlin. This isn't coming apart!

The drilling residue has piled up at the bottom. It does happen that you think a hole is OK, a hot rivet arrives, and it goes only part way in. Stress! Luckily they shrink a bit when they cool down, so if you haven't hit them too hard yet, you can usually wriggle them out again.





We worked our way along the platform side all day yesterday. Here is John on the 'barbie' heating up another rivet. They come in a number of different sizes, so it's best to ask before hand what the riveters want. Is that chairs outside the signal box?

We are now something over half way with the riveting up. Most of the platform side has been done; we still need to do the forecourt side, which needs rather fewer as it it doesn't have a fascia board.

The fact that someone has built a chimney stack right through an area still to be drilled and riveted has made things very difficult for the canopy team here. Now what?

At Broadway north we caught sight of the S&T gang fitting a beautiful finial to the newly erected inner home signal. You might say, should they be using the signal's own ladder? Well, they had that with them in the back of the truck. One thing at a time.


Putting finials on signals is thirsty work.

At lunch time, a set of patio chairs was produced from the locking room, and the kettle was on !

Finally, a little jewel from Broadway-to-be:

Heritage supporters at Broadway found a GWR station oil lamp at a railwayana auction. However, its condition on closer inspection was poor, but to our delight we were able to source an identical (non-GWR) example on Ebay, from local manufacturer Hinks in Birmingham.

You can read a bit more about Hinks here:
http://www.oldcopper.org/makers/joseph_hinks.php

The lamp is complete with burner, funnel and white glass shade, and is destined to hang from the ceiling of the booking hall. A member of the Broadway gang has expertly fitted a LED candle shaped bulb unit to it, with the supply wire hidden inside the hoop. Can you see it? It's little accessories like this that will make all the difference.


9 comments:

  1. Hello Jo,

    The oil lamp will look superb in the new station building, the whole site will be a credit to all the Broadway gang, S&T .permanent way gang etc. Can I ask, will there be a section of canopy linked to the footbridge and if so when will this be installed?
    regards,
    Graham Handley

    ReplyDelete
    Replies
    1. The footbridge was built too near the station building, and too far to one side, to replicate the layout that was Broadway.

      Delete
  2. Who was responsible for this cock-up...o.k.- you don't have to answer that! Great work anyway on the steel.

    ReplyDelete
    Replies
    1. That's not very nice. The station building is bigger than the original and the footbridge comes from another station. Maybe there is a good reason why the decision was made. This is a team of volunteers giving their time freely so criticism has to be carefully considered.

      Delete
    2. The Station building is longer than the original but I don't know whether it is wider, probably not. The bridge dimensions might be slightly different from the original, again. I don't know (many GWR structures of this period were standardised)and quite a bit of the bridge is actually new. Nevertheless, whilst it would have been preferable to have a perfect "fit" I don't think that it will detract much, if at all, from the completed station - which is starting to look superb.

      Delete
    3. I don't often feel it necessary to respond but as Jo's answer is rather simplistic and open to criticism I am adding this information. The heritage footbridge obtained from Henley-in-Arden is slightly longer than that originally at Broadway. The design does not allow small trimming so it was installed complete. Hence the slight - only a few inches - out of alignment with the front of the station building. The footbridge is located as far away from the building as the site permitted and there will still be the extended building roof to link with the footbridge steps roof. The team there work very hard to achieve as much heritage replication as possible and support not criticism is appropriate.
      Alan Bielby. Projects Director.

      Delete
    4. Alan, Thank you for the clarification. I felt very upset to see such negativity towards the
      Volunteers. Saying that someone has "cocked up" is not appropriate or warranted. The blogs are great and I always look forward to seeing progress on the railway.

      Best wishes to the team

      Delete
    5. With the misalignment of the footbridge and station canopy, what are the detailed proposals for the canopy end design? I hope that the problem will be addressed in a way that achieves as authentic an outcome as possible. Given the marvellous achievements of all concerned so far it would be a great pity to see the station building disfigured by a hastily conceived lash-up that links station to footbridge.

      Richard (shareholder)

      Delete
  3. I saw a set of lamps such as you show in your picture - but at Kidderminster Junction signal box, rather than on the station, (very closely guarded by the signalman too). Shame about the canopy/footbridge link not being possible, but the whole thing looks great and should not be detracted from. Regards, Paul.

    ReplyDelete