This way to the jungle |
Although we consented to follow Steve, it was still a small fleet of cars that hesitantly entered this field of waist high weeds, with Steve heading the charge. He does have 4 wheel drive though, and he could dig his way out of trouble. Not so the Polos, Renaults, Audis and even a Vauxhall van that tried to follow.
Next came an enormous tangle of abandoned fencing material, which Steve scooped off the embankment slope, to give us a route to scramble up. It was like the cat had got your mother's knitting!
After a short trip with the Landie down to the sewage farm, we found the rail head as left last Saturday. The last two rails were there, and the empty rail wagons can be seen in the distance. We have just started to lay into the curve into Broadway.
The gang is all dressed up but with nowhere to go. Pesky teenagers not only broke into our mess coach, but they went and stole our rope for marking out the line where the sleepers are laid. They left behind numerous plastic wrappers for orange squash and ice cream.
The rope isn't worth much, but when you can't lay without it, it is priceless.
We hunted round the site to see if we could find it abandoned somewhere, or if there was more rope available in the site safe, but no luck.
In the end, we set off with this 'wooden rope' where Leigh and Peter lay out some battens along the ground. It got us out of trouble and we were able to start laying the remaining 150 or so sleepers left on the train. Necessity is the mother of invention...
Then Alan arrived with the Telehandler, laden brimfull with 12 sleepers. Great stuff, we can get going.
We put in the first 26 in order to lay the last two rails, but before doing so, we needed to square them up. Now that we are entering a curve, the inside rail keeps trying to overtake the outside rail.
Then we are ready. Steve drags the last pair of rails on to the new stretch of sleepers, until Paul signals that they have come far enough.
Whoa !
The last pair goes in, we are 18.2m nearer Broadway again. In the distance you can see the Telehandler approaching with another load, while behind the camera the other half of the gang continues to lay sleepers. We need to empty the bogie flats, as arrangements have been made to fill them up again as early as this Monday.
Then comes the interesting bit. With this last pair of rails we come to the end of the next 1000m of CWR, and also the last bit of continuously welded track. For this you need an expansion gap, provided by an installation known as a 'breather'. Or as us from 'darn sarf' would say, an 'eavy breaver'. It's two pairs of rails with tapered ends that can slide into each other. Steve here brings down the first pair.
The first rail with a tapered end is lifted into position on a further lot of concrete sleepers. The pointy end is nearst the camera, can you make it out?
Then comes the central section, mounted on four timbers and fitted with special chairs that allow the rail ends to slide to and fro with the expansion caused by the varying temperatures.
The tapered rails we use have obviously been installed before, so have an old weld at the butt end. This has to be cut off, as we cannot have two welds next to each other. This could lead to fractures.
The central section is then placed into position at the end of the CWR track section. How lucky we are to have that JCB, this is heavy stuff.
Finally the first tapered rail is carefully laid into the special chairs.
They have angled plates bolted to them, which hold the rail down, but allow it to slide back and forth. The two bullhead rails in the middle just hold the whole thing together.
Time for lunch...
Now to get out of that field with the waist high grass again. This car had to have 2 goes at the slope at the end, in order to shoot out out on to the road, under the guidance of a banksman.
Lunch was in the mess coach, now safely back at Toddington. Sadly it is clear that we can't leave it out along the line, even if half a mile from the nearest access point. Jim treated us to sausages, chips and beans, while Mrs. B tempted us with a chocolate, and a raspberry sponge cake. Oh, the choices. Of course, you could always have both...
Returning to Toddington (and the 'real world') we found no fewer than three coaches in a very full car park, and, during a quieter moment, this lovely scene with the delightful 1450 and 'Chaffinch' the auto coach. Enjoy it while it lasts, they'll be going home again soon.
Back in the new PWay car park at Childswickham.
Doesn't this scene remind you of the Klondyke gold diggers doggedly climbing up the frozen hillside?
Both Toddington end breather rails are now in, and here one of the Broadway ones is being wriggled into place. The distance between them, represented by a diagonal gap, is calculated from a formula in a book.
When the rails are where they should be, they are bolted down with the nut runner.
Here it's the turn of the Malvern side.
Just about finished here with our breather joint. Paul holds the last plate, due to go on to the 3 bolts at his feet. Can you see how the rails slide past each other? Wheels that pass over the top do not feel this joint, and there is no 'clickety click'. From here on onwards, we will be laying alternate welded and fishplated joints, i.e. rails of 120 foot length.
What about the sleeper laying team? They have noticed that the sleeper laying beam, when suspended from the JCB boom, is just about the same height as the bar in the 'Royal Oak' at Greet (a pub we know well....).
OK then, alright, we'll lay a few more. Got to empty that train. The view here has moved on a bit, no more Peasebrook farm, this is Halling's garden machinery business on Pry lane. That's a Broadway address!
On the other side we have moved on past that sewage works tower. It's not a pretty sight, but it does a useful job for the community.
Here's the breather joint fully installed, with central section and all 4 rails cut and clipped into place.
Beyond the sleepers continue for a few more lengths, but we've run out of rail. No worries though, more is coming on June 12th, just over a week from now. And at Gotherington there is more than a complete trainload of sleepers, all ready and waiting to be loaded.
Our final look today. The end of the sleeper run is a stone's throw from Pry Lane bridge. That's only 2 more panels, something we will easily achieve next time. Note that, as we approach the goods shed in the trees, the new ballast starts to swing over from the LH to the RH side of the former double track.
Dunno about the Klondyke. It does remind me of the film 'The Titfield thunderbolt', where they scurried to get water from the stream for the loco! Also, I had to laugh with the mention of the 'Breather' in the same sentence as the 'Sewage works'. Have seen many breathers on BR but never seen one installed before. Very interesting. Regards, Paul.
ReplyDeleteShame about the mess coach, can't people leave anything alone. Can't it be taken back to Toddington at the end of the day, or use the facilities at Broadway now that you are near there. You could do with something as a shelter in case it came on to rain. Very well done you will soon be at Broadway.
ReplyDeleteWell done to everyone! You are nearly there! Can't wait to visit the railway on a train to Broadway! :D Aaron
ReplyDeleteI,rode on the Auto,to just beyond Little Buckland bridge,today.Nice to glipse Broadway goods shed,in the distance!.I,noticed,that there are still some bits of rail,at Laverton!.Will these,be used at Broadway!.Or are they going elsewhere?. Anthony.
ReplyDeleteOn Saturday, the 3rd June 2017 I was in the privileged company of the PWay gang, as they travelled on the last train back from Cheltenham.
ReplyDeleteI spoke with one group and we were talking about the seat post height for riding a bike. I mentioned Bernard Hinaults’ book and on page 62 of ‘Road Racing Technique and Training’, the calculations are as follows.
The fraction calculator is 0.885.
Where;
Hs = 0.885 x E
Hs equals saddle height measured from the centre of the bottom bracket axle to the height at the top of the saddle.
E equals the inseam, the distance from the floor to the crutch of the bike rider.
I promised that I would post it on this thread.
Mark.
The excitement is getting to us all as the target of Broadway gets even closer! As for Anonymous, what? try this one instead, E = PW2 where E = distance to Broadway, PW number of miles walked by the PW Team,2 = number of tea's required to get to minimum momentum for track laying. I will bring the answer to the PW team when I visit in two weeks time with the doughnuts!!!!
ReplyDeleteRegards
Paul & Marion
Paul & Marion,
DeleteSome members of the PWay team will understand the significance of 0.885, as we discussed this fraction calculator in the carriage on the train. I wasn't certain of it and I thought wrongly that it was 0.833.
BTW, not only do they need doughnuts, they also need some string....
Mark.
O.K. anonymous, I will take the doughnuts and a large ball of string to them!!! is that OK with you JO?
ReplyDeleteRegards
Paul & Marion
Paul & Marion,
DeleteMy name is Mark.