Wednesday 17 April 2019

Fire ! ( - buckets)

Monday at Broadway

A good, dry and not too cold working day for us. Unfortunately the morning was a bit of a write off as two of us were in a meeting, while the third (a-hem) had a rare appointment with a plumber, and rarer still, he turned up ! So we made a very late start.




Just before lunch we all met up on the platform, and thought we'd get an hour in before attacking the sandwiches.

With the scaffolding now cantilevered out, Neal was able to make a start on fitting the outer, upper boards to the corners.







We spent some time making room for the last board; it took a while before we had that sheet of corrugated iron off.

With the sheet stored in the centre span, Neal was able to cut into the corner to fit the upper length of timber.





And there we have it, at the end of the afternoon the three missing boards on the forecourt side of P1 were fitted.

A beaming Neal can be seen looking at the camera, proud of his work.

In this overall view, taken as we were tidying up, you can see that all but one of the timbers for the roof of the steps have been fitted, and indeed primered and put in undercoat.

What are the next steps then? In principle the fitting of the dagger boards, up and down the steps. They are a bit more complicated than those along the canopy, there are 4 different types to make. The dagger boards will be produced by the Broadway gang, and as soon as they are ready, we will fit them.

If there isn't (yet) a supply of dagger boards next week, we will be fitting timbers across the roof boards, and these will support the corrugated iron sheets when they go on. And of course we have the final timber to fit on P2.


Fire !

Now, looking forward, the station needs some fire buckets. We have a location for these, which is up against the wall under the canopy extension. Here they are out of the way, yet accessible in case of fire. They will be in the dry, so not prone to rusting or leakage.

This is the rack at Toddington with 4 of them on, and this is what we would like to reproduce at Broadway.





Over the years we have accumulated the parts for such a rack, but they are not all the same.

In fact we have enough brackets, but they are of three different designs. Some are welded steel, some wrought iron, and another is cast.



Our question to readers of this blog is, is there anyone out there who can give us one or more of any of these brackets, so that we can try to assemble a set of identical ones?

Possibly we could swap?






We already have three original fire buckets, thanks to two donors. One even has GWR embossed on it. We need one more. Note that fire buckets are a bit longer than normal buckets. Anyone out there who can help us with a spare? Email: breva2011 (at) hotmail.co.uk


History corner:
On the Early GWSR Flickr site more of John Lees' track laying photographs have been scanned in and published.

You can see the latest batch on pages 7 and 8:

https://www.flickr.com/photos/73536293@N02/albums/72157664738875108/page8

On 30th December 2000 the first PWay train rumbled into Cheltenham Race Course station.

17 years later, the first PWay train (with many of the same gangers) rumbled into Broadway!

https://youtu.be/aGU4TTG5YTE

More news on the Winchcombe goods dock on the Heritage Herald blog:

https://haylesabbeyhalt.blogspot.com/2019/04/caught-smoking.html


4 comments:

  1. There appears to be a supply of GWR brackets on eBay if it's of any use: https://www.ebay.co.uk/itm/Cast-Aluminium-GWR-Fire-Bucket-Holder-/161910946876

    There's also been a fire bucket lying around in C+W for ages in the paintshop that no one's laid claim to, no idea if it's GWR or not though.

    ReplyDelete
    Replies
    1. The Ebay ones are for miniature gauge railways.
      I will have a look round the C&W shed at an early opportunity for the bucket. Many thanks for the tip, hope they don't pour cold water on it :-)

      Delete
  2. Could the steam loco dept. help you out with some brackets? They start out as flat bar and then with heat and a hammer.......
    Regards, Paul.

    ReplyDelete
  3. Visited the line on the 17th April 2019.

    Saw the PWay team working in Winchcombe on the new siding.

    Impressed with the quality of the chairs and tables in the Café. Everybody has made a fantastic job getting that up and running. Very impressed.

    Enjoyed the train rides immensely.

    ReplyDelete