Thursday, 1 June 2017

Part 2 of the canopy goes on

Today we erected the second half of the steelwork on the heritage Broadway station canopy. It all went up very easily, fitted perfectly, no issues to report. Piece of cake, this heritage stuff. Turns out is was cheaper than the contested first design too.




Prior to the big erection day, the team had been down to position the purlins, fascia boards and intermediate rafters around the station building.

Here you can see a row of them placed along platform two, ready for the Vic Haines lorry to lift them in.

There was just a small team of 4 on site, but everything went very well indeed.






We started on the forecourt side. You can see one of the purlins going up here.




It was accepted at the top, and with a bit of to-ing and fro-ing it was supended between two trusses.

The crane lorry driver is on the right, and he controls the lift from a box around his waist.








The second item to go up was an intermediate rafter, a short piece that connects the ridge purlin to either the ringbeam (here) or the fascia board (platform side).

It is wriggled through the purlin in the middle.





With all the purlins correctly located on the forecourt side, the lorry reversed - with some difficulty, half of the trackbed being blocked - into the platform 2 road between the platforms, and lifted in one of the platform side purlins.





This was followed by another of the intermediate rafters, which was steered through the gaps between the scaffolding poles.








The intermediate rafter was pushed into contact with the ridge through a gap in the purlin. This was quite tricky, but it did fit in the end. The bottom end of it connects to the platform side fascia board, once that has been lifted in.





Last of all, a fascia board is lifted in. These are quite heavy.

There is no natural place for them to hang, so they are supported on jacks and secured with G clamps for the time being.







With the fascia board supported and clamped, a mag drill is used to bore a bolt hole through three layers of steel.

The fascia board is then bolted on at each end, and later on we will change these temporary bolts for proper rivets.





Here's a view of the forecourt side of the canopy, with everything now bolted on. There are no fascia boards on this side. You can start to see how much of the canopy structure is up here now.

On the original building, all this steelwork rested on sandstone blocks on top of several rows of brickwork. In our construction, necessary due to the requirement for insulation, the walls are hollow so the canopy rests on an invisible internal frame. The forecourt side of the frame can be seen here above the blue plastic sheet.

When the purlins go in, they are placed on angled brackets half way up the trusses. There's one already in place on the right, and we're pleased to say they all met at the right place.

Note how the top half of the purlin goes over the truss, and the bottom half under it.

Platform side, the top half above the purlin is glazed, while the bottom half is corrugated iron sheets. Forecourt side, everything is corrugated iron sheets.


Another purlin and another fascia board go in at the northern end:






The fascia boads were made up in 3.5m lengths, then joined together in 7m pairs, and these were then lifted up into place. Here you can see one about to  be married to another, again with bolts to start with, to be replaced by more solid rivets in the next stage. This is the last one on the northern end, the assembly job having started in the middle to avoid distortions.

This is a view along the line of ridge purlins, with everything that is in sight fully assembled. Big, isn't it!






Near the end of the afternoon, the last purlin is walked to its final postion, at the Signal Box corner.






And the last fascia board is secured to the ends of the trusses and intermediate rafters.

It is amazing that everything fit without trouble, and is nice and straight. On the first assembly day we skimmed 1/8th inch off one of the ridges; today we cut nothing off at all, it all just went into place without grumbling.

Today we had the Vic Haines lorry to do the lifting; in 1904 and with the track already in place between the platforms, a rail mounted steam crane would have been used. In 1904, the whole structure would have been test assembled in the E. Finch yard at Chepstow, so that no holes would need drilling on site, just riveting up.

Here is the full length of all the fascia boards together. Outside will be dagger boards and a gutter, inside you will see the steel and two  original works plates.

Our hearty congratulations go to the gang in the loco department who went for the heritage option, designed it, manufactured it, and finally erected it. Well done, lads!

We also thank our shareholders who helped pay for it, but look what quality you got for your money!

With all the assembly work done, a fair number of holes still remain to be drilled ( a bit under 500 in fact, but many have already been done) so here are some pictures of the finished product:

A view through the canopy, from the southern end
The completed canopy, from the signal box steps.  It's still a bit difficult to make out though, with all the scaffolding in place. Wait until the sheeting is on, and the scaffolding removed, then it will look even better. It should all be done by September.

A view from under the tree on platform 2
A few steps further back, a shot through the footbridge centre span. If only we could see it from above....
Mysteriously, a ladder appears and then this 'aerial' view is possible.
A last view, from above again. Everything is now in place, or at least everything major. Some corner brackets still have to be made, and the canopy overhang at the front here, which should rest on the bottom of the footbridge steps. This allows passengers to cross the line, walk down the steps and out from the platform, all under cover. Toddington didn't have this, but a good example can still be seen at Hall Green.
Impressed? It was worth going the extra mile for a heritage job of which we can feel proud for many years.

Finally, a quickie looking north, just to show you the freshly ballasted northern section of the track, where there will be double track to see, incorporating two turnouts and two buffer stops at the end. Three signal posts are in place now.


Wednesday, 31 May 2017

Welding and stacking

Two teams today - one at Peasebrook on the extension, the other at Gotherington in the sleeper depot.

We met in the mess coach, which appears to have received the visit of some uninvited individuals, as we found one of the doors open on arrival and a fire extinguisher partially discharged. Fortunately, no real harm seems to have been done.

We then split up to repair to the two locations.

The Peasebrook team looked after the welders again, who came to weld up the rail recently laid, which continues to motor away from the stretch that has now been released for general use. While the track layers are nearing Pry Lane, the welders today started from bridge 4 at Peasebrook Farm, just visible by the white handrail on the right of the picture. The number of welds achieved by the two teams on site (only one in the picture) was 12 at the end of the day.




Meanwhile, team 2 at Gotherington, a 'gang of four', attacked the shrinking pile of jumbled sleepers with vigour. The current daily record for sleepers stacked is held by the Saturday gang at 200.

Here Martin carefully inserts the forks into a gap near the middle of the pile - how many sleepers would he catch?






It is a bit like fishing. Here he has caught six - a respectable number - but the sixth one is a wobbler and looks like falling off. These then invariably rotate so that on the next visit you find them lying end on, a tricky job for the Telehandler with its fixed boom.




Foremarke Hall trundled past into Gotherington today, with a nice 'Cathedrals Express' headboard.




An hour later it was the turn of the DMU, and now the left hand pile looks astonishingly small. Remember the photo with which you were asked to guess the number of sleepers left? That pile has almost gone here. The next one also looks quite small now....









When it was Bob's turn in the Telehandler, he had the pleasure of extracting the very last sleepers from the left hand pile, which has now officially gone!









This is what it now looks like, without the pile alongside the running line. Four piles left, where there used to be five. And there isn't much left in the second pile either.

We did 100 sleepers before lunch.





Lunch was taken sitting on the bridge, from where we had an A1 view of all the trains passing by. Foremarke Hall accelerated out of Gotherington with some gusto, which was very enjoyable to hear.





Another DMU run, as the team considers whether we should have a go at clearing the second pile as well. Some of the sleepers there have rolled off into awkward positions.






With yours truly as lookout, it was possible to take some fine photographs of our Hall, here slowing down through Three Arches bridge as the train pulls into Gotherington.

As we dug into the very rear of the piles into what some called the jungle, we found this sleeper with a defect (or is it?) that we hadn't seen before - a tree root had grown right through the Pandrol hole! Unfortunately we didn't have any tools with us to try and extract this.


With still half an afternoon left, we ploughed into the remains of the second pile as well.

Bob here is fishing around in the jungle for those sleepers that have rolled off the top and right into the back.

The DMU pays us another visit, but we are now one row removed and feeling more comfortable with the extra distance between us.



At the end of the day, and with a little gentle persuasion to Bob, we cleared the second pile as well. We left a little later than usual (Andy P whizzed by with a beep-beep in the red Transit on his way home, and so did one of the Peasebrook crew, also on his way home) but with a big feeling of satisfaction - 194 sleepers stacked ready for loading, two sleeper piles completely cleared, and a total of 414 sleepers in stacks of 20 on site. Now where's that extension train?

**************

A question arose the other day: What was the line speed of the Honeybourne line in BR days?
We asked a former steam driver for you, and this was his reply:


I’m not exactly sure about the line speed. But I’d say it was around 80mph. (The Birmingham - Swansea Dmus were limited to 70). At the South end of Greet Tunnel there was a speed limit of 50mph around the curve. The Cornishman with a Castle would certainly be doing 75 to 80mph most of the way between Honeybourne East and Cheltenham.

So it was a pretty fast line, but that is to be expected, as it was a very late build, and has an easy profile and large radius curves. It would be interesting to know what speed the iron ore trains were doing. We have a photograph of a 9F with such a train, and it looks quite fast. Former residents at Broadway told us of vibrations that affeted the laths in the ceiling, and a gas mantle that fell out as these heavy trains thundered past.


Soil nailing progress
The soil nailers at Broadway had gone home at the end of the day today, but from the pictures you can make out that they have covered approximately two thirds of the area they are going to do.





Progress looks good,  and the weather has certainly helped.

They are currently working by the goods shed, and the first third or so has also been completed with the caps and the wire netting.

Saturday, 27 May 2017

A kettle in sight

A cold, breezy day today, very welcome after the heat yesterday but after a while, uncomfortably cold - some had to go and get their jackets, who would have thought of that? It started OK, nice and sunny....

Here's where we left off, before the new sleeper supply was shunted up. The rail wagons have been brought right up to the railhead, while the sleeper wagons are where they were last time - quite a long way away now - as we can't get at them on the high embankment on which we are working until the Childswickham bridge.

This is your gang for the day, just 13 of us. The size suits us, there is a job for everyone, and we don't get in each other's way. As we wait for the stragglers to arrive, we have a good cup of tea (or two).





We have new neighbours here, we're right next to a stable, and this is - a horse.

We said a cheery hello to each other.






To start with, there is a strap removal competition. Mike on the right calls out the 'ready-steady-go' and then we're off. There are 360 sleepers here; why the Conflat is only half full we didn't know, otherwise the number would have been 400. Perhaps it's a weight thing; 40 sleepers is 10 tons after all for the little 4 wheeled Conflat.





Here we are, all assembled at the current rail head. For those in the know, it's about 3/4 along the rape field just before the sewage works on the left behind the trees. We're now well away from Peasebrook Farm (and that horse).







Alan has been dispatched to collect the first load of sleepers from the supply train. It's miles away (well, maybe the best part of half a mile) and you can just about make it out in this picture as the dark shape on the track.

The rail wagon in the foreground contains 20 rails still. More have already been ordered, for delivery on June 12th. No pressure then...






Here's another view of the same thing, from the other side. The dip in the middle is bridge 4 at Peasebrook Farm. This area is due to be welded at the end of the month. We will be using CWR up to a 'breather' (expansion joint to the laymen) at Pry Lane bridge, the next one along, after that it will be one weld every other joint.




To start with, we have to hang the hooks on the spreader bar. It's the same thing every time, which hooks goes where? We can't leave them on, it makes the spreader bar too heavy to carry. These hooks are 'handed', there is a right way and a wrong way to put them on. And, no, it is not sufficient to just turn them round the other way.
The team puzzles over the arrrangement, until Bert Ferrule brings sound advice.


One small team sets off towards Broadway with an essential task: determining the exact line the sleepers will take. They hammer in these battens, and for the shorter distance by the sleepers we use a rope, which is pulled forward (in a rather satisfying way) every now and then.

Is that a curve we can make out? Is that really the start of the curve into Broadway station?




Alan then arrives with a respectable pile of sleepers, 12 in this case. Nigel gives directions as to where they are to be stacked for a short while.

To save time while the JCB was elsewhere occupied, we did a couple of stacks 'on the side' as it were. Later, when the JCB was back and the Telehandler took a long time to get to us with the next load - the distance from the sleeper wagons getting longer all the time - we used them up again. In this way we made rapid progress today, which was very pleasing. And all this while Gala was in full swing, we didn't even go and look (although bits of it came to us, as you will see in a moment).




Then off we went, laying.

The hooking up team steps well back as the jumble of sleepers leaps up from the stack, and dangles into a sort of shape.






Instructions to Steve for the jib movement are:
Toddington!
Broadway! 
Malverns!
Cotswolds!
and a new one we heard today:
Oh heck, we'll have to bar it...





We did 160 sleepers by lunch time, which could well be a record. An early start, good weather, a plentiful supply and two machines with no hitches/punctures contributed to this success.

In the background is the rape field, with in the bottom corner the hedge around the sewage farm - we are now next to it.



Boosted by the laying success before lunch, we decided to lay in a few rails as well. There were 20 left on the wagon, enough for 10 lengths (260 sleepers).

But what's this in the background? Steam? A kettle? A surprise gift to visitors to the gala was the part opening of the extension. The stop board has now been moved to just beyond Little Buckland bridge, and what you see is the 'Laverton' shuttle (now the Buckland shuttle?) in the form of GWR 1450 and its auto trailer, just setting off for Toddington again.

1450 and the auto coach? What does that look like on the new extension? Here they are, just setting off again from the new stop board. On the far right, the mess coach, so the extension gang is not far away. We have given visitors as much as we could. Next stop, Broadway!

As the little tank pulls the coach back south again, we see an angry sky over Cleeve Hill. This was about to hit us, after a promising sunny start.
Our cars are parked on the wide bit by Little Buckland bridge, it's the only place we can use to get to where we are working. But it is now increasingly far away from the rail head. We are scratching our heads over a new place to park, further up the line.




Back at the rail head, we surprised ourselves by how far we had come. Here Steve points out to Dave the different areas of the sewage farm, a place where Steve has actually been on a maintenance job, so he knows it well. Further back is the spire from Childswickham church, it's a new vista for us every day.





In this picture you can see the distinctive tower of the sewage farm, and how close we are now to it. One of the last two rails goes in here. At this point, we have laid an amazing 240 sleepers, an excellent result for a day's work.

The last rail for the day is dropped in. We used 18 of the 20 rails left on the wagon. The last two were dragged off and laid on the ground, so that we can now say that the wagons are clear, and ready for the next load.


During the day, Leigh did an excellent job of temporarily clipping up the newly laid rails, ready for the welding team.

Dave and Neil help by lifting the rail ends to the correct height, so that Leigh can do up the special G clamp bolts. In the background is the Cotswolds edge, with Broadway village just out of sight on the left. The barns in the middle are alongside the B4632 which follows the line.



The railhead today, with 240 sleepers laid, and after 18 rails laid in. This gives 9 lengths built today, or 164 metres. Of course it all needs properly clipping up still, and welding, ballasting, regulating, sweeping, laying out clips and pads, stressing, welding, clipping up finally etc etc etc etc etc.......

On the left the Pry Lane end of the sewage farm, and the sweep of the ballasted curve into Broadway. By the end of the jib of the JCB you can make out the pilasters of Pry Lane bridge, which we should reach next time. This is also where the breather will go, then it's a change to more fishplates again.



This picture at the end of this rather dull and windy day shows exactly what we laid today. And we are definitely on the final curve, there's no mistaking that. The track has started to swing left.

The team is loading the tools back on the Landie here. Broadway goods shed can be glimpsed at the rear. We're on the curve.



And finally: More kettles!

Yes, a real, big train on our extension. Topped and tailed by a main line steam loco, the train has drawn to a halt by the new stop board on the right. The leading loco is standard visitor BR 76017, with a 'Red Dragon' headboard. There's a head at every window, and no wonder, the extension to Little Buckland opened today.