Friday, 22 May 2015

May update

›
Laying of track has not started yet, but some more preparatory work has been undertaken, so time for a little update on the project. You...
5 comments:
Sunday, 15 March 2015

March update

›
Spring is upon us, and trains have started running again. The PWay dept. has completed the relay of the Toddington loop. It's also Moth...
7 comments:
Sunday, 14 December 2014

Clearance doing well

›
A walk down the extension trackbed yesterday taught me an interesting fact.... you can do clearance while sitting down! OK, OK, joshing t...
Saturday, 22 November 2014

More rail is delivered

›
On Wednesday the second half our our 800m order of rails was delivered to Toddington. The 40 rails came delivered over 3 lorryloads, and wer...
Tuesday, 18 November 2014

Lineside clearance progresses

›
Before the topside track clearance continues, the lineside clearance along the embankment needs to progress towards Little Buckland bridge. ...
7 comments:
Tuesday, 11 November 2014

More Clearance

›
After unloading the rail on Thursday last week, Stevie Warren continued clearing the trackbed on Friday. We walked the extension trackbed fr...
4 comments:
Friday, 7 November 2014

Rail unloading

›
The first delivery of 40 rails has now been taken to Laverton and unloaded on site. This enables the bogie flat used to be returned to Toddi...
9 comments:
‹
›